Are you working in my community?
This section is to notify customers about Columbia Gas of Maryland's major infrastructure upgrade construction projects. Smaller maintanence projects may not be posted. Please continue to check back for new construction projects, as well as updates on exisitng projects.
Allegany County
Mount Savage Infrastructure Upgrade
- Where
- The entire town of Mount Savage will be upgraded.
- Map
- When
- 4/1/2011 - 12/31/2012
- Monday-Friday, 7 a.m. to 5 p.m.
- What
- Infrastructure Upgrade of more than 14,000 feet of existing steel pipe with state-of-the-art plastic pipe.
- Details
- Project will impact approximately 275 customers
- With minimum 72-hour prior notification, customers' gas service will be turned off one at a time for several hours
- Columbia Gas will perform re-light work
- Traffic will be affected with possible lane restrictions, flaggers and arrow boards